Contact with the buyer
↓
Order collection
↓
Sample development
↓
Sample approval
↓
Costing
↓
Confirmation of order
↓
Consumption
↓
Fabric & accessories booking
↓
Master L/C
↓
Back to back L/C
↓
Preparing T&A calendar
↓
Fabric & trims in House
↓
Pre-production meeting
↓
Pattern and marker making for bulk production
↓
Cutting
↓
Numbering, bundling & sorting
↓
Production line set-up
↓
Sewing
↓
Finishing
↓
Pre-final inspection
↓
Final inspection
↓
Ready for shipment
↓
Order collection
↓
Sample development
↓
Sample approval
↓
Costing
↓
Confirmation of order
↓
Consumption
↓
Fabric & accessories booking
↓
Master L/C
↓
Back to back L/C
↓
Preparing T&A calendar
↓
Fabric & trims in House
↓
Pre-production meeting
↓
Pattern and marker making for bulk production
↓
Cutting
↓
Numbering, bundling & sorting
↓
Production line set-up
↓
Sewing
↓
Finishing
↓
Pre-final inspection
↓
Final inspection
↓
Ready for shipment
All the above processes have discussed in the below table:
SL
No. |
Process
|
Procedure
|
01
|
Contact with the buyer
|
It is the first process of a garment export order. At first, garments merchandiser has to contact with the buyer for order collection.
|
02
|
Order collection
|
Here garments merchandiser receives garments order from the buyer. Each order contains garments specification sheet for different items or products.
|
03
|
Sample development
|
After receiving export order, garments merchandiser has to develop the required products by following garments specification sheet.
|
04
|
Sample approval
|
After developing product sample, garments merchandiser sends it to the buyer for approval.
|
05
|
Costing
|
If the product sample is approved then garments merchandiser will make final costing for the product by discussing with the buyer.
|
06
|
Confirmation of order
|
Finally garments merchandiser confirms the order here.
|
07
|
Consumption
|
After confirmation of a garment export order, garments
merchandiser has to prepare consumption of required fabrics, trimmings and accessories. |
08
|
Fabric & accessories booking
|
Here, fabrics and accessories booking have done to in-house the required items for the export order.
|
09
|
Master L/C
|
Meanwhile, master L/C is opened from the buyer side and submitted to the garments merchandiser.
|
10
|
Back to back L/C
|
For importing raw materials for the export order, here manufacturer has to open back to back L/C.
|
11
|
Preparing T&A calendar
|
In the mean time, garments merchandiser has o prepare time and action plan here for the garments production.
|
12
|
Fabric & trims in house
|
All the required fabrics, trimmings and accessories are in-housed here according to the booking chart.
|
13
|
Pre-production meeting
|
It’s an important factor for a garments production. Production team should complete this meeting before staring the production.
|
14
|
Pattern and marker making for bulk production
|
Here, pattern and marker should prepare according to the approve sample.
|
15
|
Cutting
|
Fabrics cutting are done here according to the approved
pattern and marker. |
16
|
Numbering, bundling & sorting
|
Here all the cutting fabrics have to do numbering sorting and bundling to avoid shade variation in the garments.
|
17
|
Production line set-up
|
Here, production team sets a perfect production line for
completing smooth garments production. |
18
|
Sewing
|
All the cutting fabrics are sewn here according to the approved sample.
|
19
|
Finishing
|
All the required finishing procedures are done here by
following the buyer’s instruction. |
20
|
Pre-final inspection
|
Here, pre-final inspection has done to ensure right quality for the export order. Normally it is done by factory inspection team.
|
21
|
Final inspection
|
Final inspection of an order has done here by the buyer’s inspection team. Where, the inspection team is confirmed by the buyer.
|
22
|
Ready for shipment
|
Finally garments sent to the buyer by usingsea freight or air freight.
|