Prime School BD (PSBD24) is popular blog site about technology, merchandising, textile & accounting rules in Bangladesh. Also the post that are publishing about Accounting tutorial, Textile, RMG, Merchandising, Knit Merchandising, Woven Merchandising, Apparel Merchandising, Garments, Dyeing, Spinning, Washing, Buying House, else many things with tips & tricks.

Aowsaf FM

Prime School BD (PSBD24) is popular blog site about technology, merchandising, textile & accounting rules in Bangladesh. Also the post that are publishing about Accounting tutorial, Textile, RMG, Merchandising, Knit Merchandising, Woven Merchandising, Apparel Merchandising, Garments, Dyeing, Spinning, Washing, Buying House, else many things with tips & tricks. বদিউজ্জামান ( রুবেল )
Blogger Tips and TricksLatest Tips And TricksBlogger Tricks

How to Set Daily Production Target in Apparel Industry?

Production Targets Definition | Production Target Formula | Examples of Production Targets | Industrial Engineering Formula | IE Formula for Garments

Daily Production Target in Garment Industry:
Production quantity produced by a qualified worker in a day at standard performance is known as daily production target.

You may follow  Definition of Process Costing | Steps of Process Costing in Apparel Industry
Daily production target can be calculated by using the below formula in apparel industry:

Daily production target,

= (Daily clock minute/ Standard time) × Efficiency
= [{(No. of operator × working hours × 60) / Standard time} × Efficiency]
The above formula will be very easy to understand if you follow the below examples.
Readymade garment floor
Fig: Readymade garment floor
Example-01:
In a production line of Rahela Apparel Limited have 40 operators, where working hours is 10, standard time 90 minutes and 80% expected efficiency. Find out the expected production target per day in that factory.

Solution:
Here,
Number of operators= 40,
Number of working hours= 10,
Standard time= 90 minutes,
Expected efficiency= 80%,
Production target per day=?

Daily production target = (Daily clock minute/ Standard time) × Efficiency
= [{(No. of operator × working hours × 60) / Standard time} × Efficiency]
= [{(40 × 10 × 60)/ 90} × 80%]
= 213 pcs.
So, daily production target in Rahela Apparel Limited is 213pcs.

Example-02:
Number of working hours= 08,
Number of operators= 50,
Expected efficiency= 85%,
Standard time= 80minutes
By following the above points of Tawhida Apparel Limited, find out the daily production target in that factory.

Solution:
Here,
No. of working time= 8hours,
Total no. of operator= 50,
Standard time= 80min,
Efficiency= 85%,
Per day production target=?

Daily production target,

= (Daily clock minute/ Standard time) × Efficiency
= [{(No. of operator × working hours × 60) / Standard time} × Efficiency]
= [{(50 × 8 × 60)/ 80} × 85%]
= 255pcs.
So, daily apparel production target in Tawhida Apparel Limited is 255pcs.